IMPLEMENTASI METODE PERT PADA SISTEM INFORMASI PENJADWALAN PROYEK PENGEMBANGAN APLIKASI KURIKULUM OBE UNRI

Show simple item record

dc.contributor.author Febriyanti, Vira
dc.date.accessioned 2023-06-27T06:31:00Z
dc.date.available 2023-06-27T06:31:00Z
dc.date.issued 2023-04
dc.identifier.citation Perpustakaan en_US
dc.identifier.other Elfitra
dc.identifier.uri https://repository.unri.ac.id/handle/123456789/11049
dc.description.abstract The Outcome-Based Education (OBE) curriculum application development project at the University of Riau (UNRI) was one of the studies conducted by the Computer Science Lecturer at the Faculty of Mathematics and Natural Sciences, University of Riau (UNRI). The needed and objectived in the development of this information system were to maximize the integration of graduated learning outcomes and learning plans at UNRI. The research's main objective was to formulate a time frame for accelerating the development of UNRI's OBE curriculum applications. In accelerating application development using accelerated time analysis using the Critical Path Method (CPM) and Project Evaluation and Review Technique (PERT) methods. The stages in this research were literature study, data collection, CPM analysis, system design and development, implementation of the CPM algorithm into the system, implementation of the PERT algorithm into the system, and system testing. The development of the OBE curriculum application consists of 23 project activities carried out with a completion duration of 68 weeks, there were 20 activities that were critical where the work on these activities must be completed on time and no work is allowed to be behind schedule, then there were 3 activities that were not critical where the activity had a tolerance for delays in its completion time. en_US
dc.description.provenance Submitted by wahyu sari yeni (ayoe32@ymail.com) on 2023-06-27T06:31:00Z No. of bitstreams: 1 Vira Febriyanti_compressed.pdf: 306271 bytes, checksum: 8edd4b1c5eb5ef0ef4757dac07d3cce7 (MD5) en
dc.description.provenance Made available in DSpace on 2023-06-27T06:31:00Z (GMT). No. of bitstreams: 1 Vira Febriyanti_compressed.pdf: 306271 bytes, checksum: 8edd4b1c5eb5ef0ef4757dac07d3cce7 (MD5) Previous issue date: 2023-04 en
dc.description.sponsorship Fakultas Matematika dan Ilmu Pengetahuan Alam en_US
dc.language.iso en en_US
dc.publisher Elfitra en_US
dc.subject Critical Path Method en_US
dc.subject Project Evaluation and Review Technique en_US
dc.subject Critical Path en_US
dc.subject Critical Activity en_US
dc.subject Non-Critical Activity en_US
dc.subject Project Scheduling Information System en_US
dc.subject Probability en_US
dc.title IMPLEMENTASI METODE PERT PADA SISTEM INFORMASI PENJADWALAN PROYEK PENGEMBANGAN APLIKASI KURIKULUM OBE UNRI en_US
dc.type Article en_US
dc.contributor.supervisor Andriyani, Yanti