Abstract:
Along with will be held at the “Pekan Olahraga Nasional”(PON) XVIII held in
2012, the city of Pekanbaru Riau province was chosen to host the biggest national sports
event held every four years and was followed by the Province in Indonesia. By the
smoothness of the Pekan Olahraga Nasional events is pretty much Venue PON development
projects undertaken by the Government of Riau Province and one of them is the Main
Stadium Development Project University of Riau. This study aims to determine the form of
Network Planning, during the duration of the project progress, including work on the critical
path and the probability of completion of the construction project Main Stadium University
of Riau.
This study uses PERT (Project Evaluation and Review Technique) and CPM (Critical Path
Method - Critical Path Method) analyzed fatherly time planning and implementing the
optimum time.
From the results that have been made when planning had three changes. And
implementation of the plan does not comply with the specified scheduling. From planning
delayed 104 weeks to 113 weeks, so the probability of completion of the project the week to
110 probability already demonstrated its value in the normal curve at 99%, then at week 111
s / d to 113 weeks was not able to show the value of the probability of the completion of this
project suggests that the timing of the planning over the target and the target does not match
the optimal execution time so that the time spent in completing the construction of Main
Stadium University of Riau.